Project Description: This project involves two phases to replace a culvert on the 400 block of Broad Street.  The first phase has been preliminary engineering, which was completed in the spring of 2020. The second phase is construction, anticipated to begin in October, 2020.

Project Background: An old and undersized culvert on Broad Street has been responsible for previous overtopping of the road.  This site has been included in previous Town flood studies by Sungate Engineering.

Status: Active/Funded. The Council approved funding for preliminary engineering in June, 2019. Sungate Design provided preliminary engineering support.

Follow this page for updates on project status as they become available.